Project start
1 Jul 2026
UAT hand-over
11 Oct 2026
Production cut-over
13 Nov 2026
Release 1 complete
13%
Turn on editing to drag bars, add or remove items, reorder them and change responsibilities.
No unsaved changesResponsibility key
- Design Monkey — Core Build
- Data (Client)
- UAT (Client)
- Integrations (Clixz, Prodware)
- Contingency
- Key milestone
- Darker fill = progress to date
Release 1 — Launch Essentials
Everything required to receive, manage, progress, complete and financially process service work from day one.
Core build, testing and UAT
Platform functionality, testing and hand-over
Environment, data and cut-over
Production setup, imports, migration and go-live
Post-launch roadmap — Releases 2 and 3
Indicative sequencing, listed in priority order. Dates are directional and confirmed release by release.
Release 2 — Operational improvements and automation
Priority order
Release 3 — Future enhancements and added value
Priority order, scheduled from live-usage feedback
Detailed schedule
Every item on the timeline with its owner, dates and progress.
| Item | Responsibility | Start | Finish | Duration | Progress |
|---|---|---|---|---|---|
| Release 1 — Launch Essentials — Core build, testing and UAT | |||||
| NAV core integrations (customers, sites, equipment, inventory, pricing, stock, orders) | Integrations | 1 Jul 2026 | 4 Sept 2026 | 9 wks | 60% |
| Users, permissions and service-partner workflows | Design Monkey | 13 Jul 2026 | 28 Aug 2026 | 7 wks | 60% |
| Basic van-stock visibility and manual adjustments | Design Monkey | 14 Jul 2026 | 8 Aug 2026 | 4 wks | 95% |
| Engineer companion app | Design Monkey | 27 Jul 2026 | 27 Sept 2026 | 9 wks | 10% |
| Service-call management (creation, triage, allocation, status, SLA, prioritisation) | Design Monkey | 29 Jul 2026 | 18 Sept 2026 | 7 wks | 30% |
| Shared mailbox integration (two-way sync, read status, sent items) | Design Monkey | 3 Aug 2026 | 30 Aug 2026 | 4 wks | 10% |
| Engineer workflow, worksheets, risk assessments, signatures, multi-visit | Design Monkey | 11 Aug 2026 | 6 Sept 2026 | 4 wks | 10% |
| Parts allocation, live stock checks, transfer and sales orders | Design Monkey | 24 Aug 2026 | 20 Sept 2026 | 4 wks | 10% |
| Operational monitors and action queues | Design Monkey | 25 Aug 2026 | 26 Sept 2026 | 5 wks | 0% |
| Engineer timesheets, supervisor approval and accounts export | Design Monkey | 31 Aug 2026 | 25 Sept 2026 | 4 wks | 20% |
| Basic quotation creation, send and download | Design Monkey | 4 Sept 2026 | 22 Sept 2026 | 3 wks | 30% |
| Supply-only orders (email-led interim process) | Design Monkey | 9 Sept 2026 | 27 Sept 2026 | 3 wks | 10% |
| System and integration testing | UAT | 28 Sept 2026 | 4 Oct 2026 | 7 days | 0% |
| Contingency - pre-UAT buffer | Contingency | 5 Oct 2026 | 9 Oct 2026 | 5 days | 0% |
| Build complete - hand over for UAT | Milestone | 11 Oct 2026 | — | — | — |
| UAT cycle 1 | UAT | 12 Oct 2026 | 25 Oct 2026 | 2 wks | 0% |
| Refinements, defect fixes and re-release | Design Monkey | 19 Oct 2026 | 1 Nov 2026 | 2 wks | 0% |
| UAT cycle 2 and regression | UAT | 2 Nov 2026 | 8 Nov 2026 | 7 days | 0% |
| Contingency - pre-cut-over buffer | Contingency | 9 Nov 2026 | 12 Nov 2026 | 4 days | 0% |
| R1. Interactive onboarding and training | Contingency | 13 Nov 2026 | 23 Nov 2026 | 11 days | 0% |
| Hypercare and post-launch support | Design Monkey | 13 Nov 2026 | 7 Dec 2026 | 4 wks | 0% |
| Release 1 — Launch Essentials — Environment, data and cut-over | |||||
| Environment build and production setup | Design Monkey | 21 Sept 2026 | 27 Sept 2026 | 7 days | 0% |
| NAV production endpoints and integration configuration | Integrations | 28 Sept 2026 | 4 Oct 2026 | 7 days | 0% |
| Core data setup and reference imports | Data | 5 Oct 2026 | 11 Oct 2026 | 7 days | 0% |
| Red Zebra migration - trial run and data validation | Data | 12 Oct 2026 | 18 Oct 2026 | 7 days | 0% |
| Training and cut-over readiness | UAT | 19 Oct 2026 | 6 Nov 2026 | 3 wks | 0% |
| Red Zebra migration - dress rehearsal | Data | 25 Oct 2026 | 31 Oct 2026 | 7 days | 0% |
| Go / no-go decision | Milestone | 1 Nov 2026 | — | — | — |
| Red Zebra migration - final cut-over load | Data | 5 Nov 2026 | 10 Nov 2026 | 6 days | 0% |
| Production cut-over - go live | Milestone | 13 Nov 2026 | — | — | — |
| Post-launch roadmap — Releases 2 and 3 — Release 2 — Operational improvements and automation | |||||
| Enhanced inbox filtering and automated handling rules | Design Monkey | 2 Sept 2026 | 10 Sept 2026 | 9 days | 0% |
| Automated / assisted engineer scheduling | Design Monkey | 12 Sept 2026 | 22 Sept 2026 | 11 days | 0% |
| Advanced parts and stock automation | Design Monkey | 25 Sept 2026 | 9 Oct 2026 | 2 wks | 0% |
| Quotation approval and payment via B2B portal | Design Monkey | 5 Oct 2026 | 21 Oct 2026 | 2 wks | 0% |
| Advanced van-stock management and reconciliation | Design Monkey | 15 Oct 2026 | 22 Oct 2026 | 8 days | 0% |
| R2 interim testing, UAT and refinements | UAT | 19 Oct 2026 | 30 Oct 2026 | 12 days | 0% |
| Automatic order creation on quotation approval | Integrations | 21 Oct 2026 | 4 Nov 2026 | 2 wks | 0% |
| Automated PPM generation and scheduling | Design Monkey | 24 Oct 2026 | 13 Nov 2026 | 3 wks | 0% |
| Digital vehicle checks | Design Monkey | 1 Nov 2026 | 12 Nov 2026 | 12 days | 0% |
| KPI and management dashboards | Design Monkey | 1 Nov 2026 | 16 Nov 2026 | 2 wks | 0% |
| Supply-only order automation and reconciliation | Integrations | 7 Nov 2026 | 22 Nov 2026 | 2 wks | 0% |
| Expanded service-partner functionality and APIs | Integrations | 15 Nov 2026 | 3 Dec 2026 | 3 wks | 0% |
| R2 testing, UAT, refinements and release hand-over | UAT | 24 Nov 2026 | 4 Dec 2026 | 11 days | 0% |
| R2. Interactive onboarding and training | Contingency | 5 Dec 2026 | 15 Dec 2026 | 11 days | 0% |
| Post-launch roadmap — Releases 2 and 3 — Release 3 — Future enhancements and added value | |||||
| Wider customer portal | Design Monkey | 1 Nov 2026 | 15 Nov 2026 | 2 wks | 0% |
| Customer self-service warranty claims | Design Monkey | 14 Nov 2026 | 23 Nov 2026 | 10 days | 0% |
| Sales / view-only portal | Design Monkey | 22 Nov 2026 | 27 Nov 2026 | 6 days | 0% |
| Third-party vehicle-tracking integration | Design Monkey | 26 Nov 2026 | 7 Dec 2026 | 12 days | 20% |
| Central compliance matrix (engineers, partners, company) | Design Monkey | 3 Dec 2026 | 7 Dec 2026 | 5 days | 40% |
| Additional reporting, analytics and forecasting | Design Monkey | 12 Dec 2026 | 22 Dec 2026 | 11 days | 20% |
| Further customer and partner self-service | Design Monkey | 23 Dec 2026 | 30 Dec 2026 | 8 days | 0% |
| R3 testing, UAT and refinements | UAT | 31 Dec 2026 | 11 Jan 2027 | 12 days | 0% |
| R3. Interactive onboarding and training | Contingency | 13 Jan 2027 | 24 Jan 2027 | 12 days | 0% |
Release 1 build completes for UAT hand-over from mid to late September, excluding the Red Zebra data migration which runs in parallel through October. Contingency is held before UAT and before cut-over to protect the 1 November launch date.